Menu Loading...

Buy Quality Insulating Concrete Forms
 from our Value Added Distributors
 or Direct from the Manufacturer

 
FASTFOOT®  by
INSTALLATION - Over Rock
<back

Click on photo for larger image. User your browser's back button to return to this page.

 
Fastfoot® is perfect for forming footings over rocky ground.

As the fabric adapts perfectly with the uneven ground, blasting and excavator costs can be reduced dramatically. Click on each picture for a larger image.

The 2x4s screed boards are supported with with steel stakes drilled into the rock, and Fastfoot® fabric is stapled between the screed boards.

Building site before commencing blasting. Notice the spectacular 360 degree view to the surrounding mountains. The location is the highest point of a residential development above the town of Squamish, note far from the spectacular Whistler Blackcomb skiing area.

 
Installing Steel Stakes

The footings are laid out on the rock, and using a spray can of paint, the steel stake locations are marked. An electric hammer drill with a 7/8” bit are used to drill the stake holes. Each hole takes about 2 minutes to drill (in granite), with 100 holes taking 3 hours.

The contractor is blasting the high spots in order to place the building correctly. The use of Fastfoot® allows the rock work to be much rougher than with lumber formed footings as the fabric easily adapts to the uneven rock.

 
The steel stakes are placed into the holes, and the 2x4 screed boards screwed to the metal stakes at the correct height. Set the 2x4s at the minimum grade to clear the rocks, as footing thickness is not typically a requirement when forming on rock.

If the holes in the metal stakes are not located at the correct height, use a 3/4" conduit strap. Click here for more information.

Drilling & installing steel stakes, 2x4s
The contractor has used conduit straps to attach the steel stakes to the 2x4 screed boards at the correct height. Fastfoot® will easily fill in the gaps by the steps, saving valuable lumber and time for the contractor

 
Installing Fastfoot® Fabric

Fastfoot® is pulled between the screed boards, and stapled in position using a hammer tacker with 3/8" staples. Special adjustment lines on the fabric ensure adequate fabric is allowed for deeper footings.
 

Installing Fastfoot®
The fabric is perfect for forming to the uneven rocky grade. Lumber and labor costs are reduced dramatically.


 
Placing Concrete

Concrete was placed using a concrete pump. Stripping time was minimal as the concrete didn't touch the lumber or stakes. Stakes were easily removed because concrete did not seep into the drilled holes.

Overview of Pour: Here is the completed pour, just after the concrete was finished flush with the screed boards.

 
   
 

Fastfoot® vs. Lumber: Cost Analysis of Project Above

The following table details the additional costs associated with each method. Fastfoot® saved the owner $5,975, primarily due to reduced blasting and excavation. Forming labor and materials were also reduced considerably by using fabric.
 

Item Lumber Fastfoot®
Site preparation - extra machine, blasting $4,925 $      0
Forming labor - extra       600          0
Forming lumber - wasted  450          0
Fastfoot® fabric          0      150
FASTFOOT® Savings $ 5,975 $   150
 
Home : Why ICFs? : Why BuildBlock? : Products : Pricing : Technical : Support : News & Events : Projects : Contact Us

Phone: 405-840-3386   |   Toll-Free: 1-866-222-2575   |   Fax: 831-597-0792